January brought significant advances in the conversion of locomotive 493 from coal-fired to oil-burning. The most significant progress was in the re-installation of the four driving wheels and the removal of the lead and trail wheels.
Installing Drivers: The Process
The process of installing drivers is one that occurs 2-3 times annually for the D&S roundhouse shop. It is an established procedure that involves lowering the driver complete with journal boxes already installed into the pit, spotting the locomotive over it, removing the binders (bottom removable section of the frame), removing the rails above the pit, lifting the driver into place, putting the rails back into place, installing the bronze shoes and wedges, and finally reinstalling the binders. This exercise is repeated four times and the full process takes an entire day.

Nick Breeden adjusting wedges
Spring Rigging:
After installing the drivers, the next step is to “lace up” the spring rigging, install all the suspension, which also allows for the removal of the shop dolly wheels, and then reinstall them under #481, the next locomotive scheduled to receive driver work.

Scott Valentine and Anthony Maze dropping wedges and prepping for spring rigging install
Spring work is accomplished by lifting the engine up on jacks. It often requires loosening the newly-installed shoes and wedges to allow the drivers to move freely in the frame when lifting the engine. Engine #493 was only “laced up” on the drivers and chained down to the frame ahead of the first and behind the last drivers in order to keep the suspension off the lead and trailing wheels.

Anthony Maze and Will White dropping the pony truck
The process of removing these wheels is somewhat similar to removing the drivers with the exception that the entire lead and trailing frames are removed with the wheels. Once out, they are cleaned with a pressure washer and then sent to the machine shop for rebuilding. They are now in the process of being rebuilt.

Scott Valentine cleaning the trailing truck
Running Gear:
Additional running gear work is well on its way to completion. Pistons and rings, valve rings, crossheads, rod brasses, and brake rigging have all seen significant work.

Joe Dailey polishing piston rods
On the boiler side of things, the stay bolt conversion is progressing nicely with about 2/3rds of the conversion completed. Other than stay bolts and the installation of the tubes, much of the boiler work is complete.

Andy Begay cutting stay bolts
Lastly, various other components are complete or well underway. The cab is finished and awaiting installation. The cab floor and running boards are under construction; the rear tender beam is close to being installed. On the appliance side, the water column, water glasses, steam fountain, lubricators, dynamo, and blowdown valves are all completed.

Charlie Moore finishing up an end beam

Last Ride of the Season: October 26th
Due to significant recent weather events, The Durango & Silverton Narrow Gauge Railroad had a slide at milepost 486.0 just north of Needleton which resulted in the tracks being covered with rock and debris, making train passage to Silverton impossible. Due to this, we have had an interruption of service to Silverton and both Silverton trains have been rerouted to Cascade Canyon for tomorrow, July 3rd. resume service to Silverton on July 4th and will be communicating with guests if there is any change. Our maintenance of way crews are actively working to clear the slide and to restore the tracks.
We look forward to restoring full Silverton service on July3 3rd.
We think so, but we’re also a little biased. We’re incredibly thankful to be nominated as one of the “Top 10 Scenic Train Ride in North America” by USA Today! From today until May 13th, you can vote for your all-time favorite scenic train. Do you think we deserve this honorable merit? Then click the link below and vote for the Durango Train! Throughout the duration of the voting period, fans may cast a single vote each day leading up to its conclusion.

We are now operating daily and our train schedule has in fact expanded as we’ve moved deeper into the summer season.
We experienced a brief pause in railroad operations recently while we worked through communications with the Forest Service on our operating status while observing agreed upon fire precautions. Concurrently, we were able to rebook passengers to adjacent days when train excursions were operating.
All trains scheduled for Thursday, June 16 and beyond are operating as scheduled at this time.
Please know that if we experience any interruptions in service due to future fire precaution levels, we will reach out to all of our guests in a most timely manner to offer information and alternatives.
Thank you”
You can see how this popup was set up in our step-by-step guide: https://wppopupmaker.com/guides/auto-opening-announcement-popups/